Illustrative use case · Production planning

Deliver on time with fewer changeovers.

The decision

A machine schedule showing what runs when, the changeovers required, the personnel and setup cost, and when each order will be ready. Short-notice changes are replanned with the same rules.

Illustrative scenario. No measured client result.

Production-line schedulingInteractive example

Personnel and setup cost

CHF 11,350

6/6 orders on time, CHF 6,018 less than the order-book plan

Family 1Family 2Family 3SetupMaintenance
Personnel
CHF 8,730
Setups
CHF 2,620 (6 h 30 min)
All orders finished after
29 h 45 min

Order C, Machining: 11 h to 13 h, 1 h setup. Complete at 18.75 h, due 24 h.

6 orders, 4 stages, identical constraints in both plans. Personnel: CHF 72 per operator hour while a stage is staffed.

Planning example: six orders pass through cutting, machining, coating and packing in a common sequence. In both plans an order starts only once its material is released, each machine handles one order at a time, setup and processing run without interruption, and the same maintenance window applies. Each stage is staffed from its first setup to its last operation at CHF 72 per operator hour, and each family changeover has a fixed cost. The optimizer compares every common sequence: first total lateness, then personnel plus setup cost, then completion time.

Situation

On a production line with fixed stages, order-book sequencing can cause repeated changeovers, idle crews and late orders. Rush orders, late material and machine breakdowns change the plan during the week.

What we built

Sequence orders across the fixed stages of a production line, accounting for machine capacity, product-family changeovers, material availability and planned maintenance. Compare schedules under the same conditions on due dates, personnel cost and changeover cost. When a rush order arrives or a machine goes down, the model replans the remaining work with the same rules, so planners can check a new delivery date before they commit to it.